| The
Mayor introduced Gene Keller, NJ DEP, and Keith
Watson, U. S. Army Corps of Engineers, to give
an overview of the seawall project.
They stated
there was one authorization to cover the seawall
and the beach renourishment. This enabled the
projects to take advantage of the fact that they
were projects in process and therefore got around
the Congress "No Start" policy.
The projects
involve the cooperation of federal and state agencies.
Keith Watson was involved in the project when
it started in 1988/1989 and it has taken this
time to bring everything to fruition.
The seawall
project has been put out to bid and the bids were
due on August 25. A panel will review the bids,
and the contract will be awarded in September.
The project must be awarded this fiscal year.
The residents play an important role.
Construction
will start in October/November and will take one
year. The contractor will decide where to start,
however, with some of the environmental restrictions
it is likely that work will start at the 8th Street
jetty and work west. Only a limited amount of
wall can be worked on at one time so that only
a few homes at a time will be disrupted. Construction
in the Avalon environment is very difficult.
The borough
solicitor has distributed papers outlining temporary
easements to allow contractors to get onto property.
These easements will be for two years - the year
the project will take and a year thereafter. All
property owners have granted an easement, otherwise
the project would not occur. The Corps wants to
have the least impact on the properties.
A question was
asked whether the temporary easement document
would include restoration of any damage to dunes
and personal property to the way it was before
the project started, and who would be responsible
to make sure the damage is taken care of? The
document provides that any damage will be repaired
at the expense of the contractor. It will be enforced
by a bond. A formal complaint should be made to
the field office local to the project or through
the mayor's office. Final payment will not be
made until the Corps and DEP is satisfied that
any damage to property has been taken care of.
Photographic evidence will be taken before and
after the project to ensure there is no damage.
The easement will not permit for heavy equipment
traffic. It will be for foot traffic and to rest
stones until they are used, and for clearance
of the crane. Construction will take place from
the ocean.
The funding
and permits are in place for the project. President
Bush has included $9 million in his budget for
a 4500-foot sea wall in the inlet at the north
end of the island. The state will pay the balance
of the $13 million cost.
The existing
sea wall will be torn down and stone that meets
specifications will be used in the new wall. The
bulkhead will remain. It is not normal practice
for any sea wall projects carried out by the Corps
of Engineers to be capped. A rough rock surface
is usually left.
|